(PRO_ERC_18/004)PRJ / Case study

Kharj Project of the Ministry of Transport (205101061)

Infrastructure Works

ClientBEC

Overview

A Ministry of Transport roads package in Al-Kharj covering the full road build-up, drainage, security and landscaping scope.

Scope

  • Base layer (55 cm) & asphalt base layer (7 cm), incl. MC1
  • Installing curbs & protections on both sides of the roads
  • Entry & exit security gates
  • Cultivation incl. irrigation & workshops
  • Rectangular concrete channels, box culverts & concrete bases

Engineering Challenge

Delivering a complete road corridor — structure, drainage, access control and planting — to Ministry standards within a fixed programme.

Delivery & Outcome

ERCAN executed the layered road build-up with MC1 prime coat, cast concrete drainage channels and bases, installed curbs and security gates, and completed irrigated cultivation.

A finished, standards-compliant road corridor delivered in fifteen months.

Related Service

Infrastructure Works

Profile register

Cross-reference from the LIST OF PROJECTS in ERCAN PROFILE2.

  • Kharj Project of the Ministry of Transport, 205101061BEC / BEKEEN · 7,332,000 SAR · Complete