(PRO_ERC_18/004)PRJ / Case study
Kharj Project of the Ministry of Transport (205101061)
Infrastructure Works
ClientBEC
Overview
A Ministry of Transport roads package in Al-Kharj covering the full road build-up, drainage, security and landscaping scope.
Scope
- Base layer (55 cm) & asphalt base layer (7 cm), incl. MC1
- Installing curbs & protections on both sides of the roads
- Entry & exit security gates
- Cultivation incl. irrigation & workshops
- Rectangular concrete channels, box culverts & concrete bases
Engineering Challenge
Delivering a complete road corridor — structure, drainage, access control and planting — to Ministry standards within a fixed programme.
Delivery & Outcome
ERCAN executed the layered road build-up with MC1 prime coat, cast concrete drainage channels and bases, installed curbs and security gates, and completed irrigated cultivation.
A finished, standards-compliant road corridor delivered in fifteen months.
Related Service
Infrastructure Works →Profile register
Cross-reference from the LIST OF PROJECTS in ERCAN PROFILE2.
- Kharj Project of the Ministry of Transport, 205101061BEC / BEKEEN · 7,332,000 SAR · Complete