Pipeline civil works at the Khurais Central Processing Facility serving the Mazalij and Abu Jifan lines.
Scope
- Backfill with cutting-resultant materials to contract standards
- Grading, cleaning & levelling
- Compaction
Engineering Challenge
Reinstating pipeline corridors to contract specification using cutting-resultant materials.
Delivery & Outcome
ERCAN executed engineered backfill, grading, levelling and compaction along the pipeline routes.
Pipeline corridors reinstated to standard over a one-year programme.